To begin with, not much work done this week aside from the completion of the tiling on the wet areas. Bath tub and laundry tub were installed.
Skirting were ready to be installed.
Now, to be on track, we have another 4 weeks left before Practical Completion Inspection. What is expected for next week should be the completion of the painting, electrical/plumbing and fix out carpenter to finish off.
To cap off, here's a photo of the house after week 27. Nothing has changed in the exterior though.