Timeline

19-07-2014  Reservation of land
12-08-2014  Deposit for land
10-11-2014  Stam Duty Paid
22-11-2014  Tender requested
18-12-2014  Tender Presentation Appointment
12-01-2015  Requested for re-tender
09-02-2015  Re-tender received
11-02-2015  Tender deposit 
09-03-2015  Variation 002 received and accepted
12-03-2015  Colour Selection Appointment booked for 16April
04-04-2015  DA drawings received in mail for signing
09-04-2015  Post Contract Variation (PCV) 001 received and accepted
16-04-2015  Colour Selection and Aircon Appointment DA Drawings signed
21-04-2015  Variation 003 received
22-04-2015  Electricals Appointment
05-05-2015  Amended Variation 003 received and accepted
06-05-2015  Variation 004 received and accepted
13-05-2015  Post Contract Variation (PCV) 002 received and accepted
19-05-2015  Contract signed, 5% Deposit paid
26-05-2015  Electrical quote signed and 50% deposit paid
28-05-2015  PCV 003 and 004 received and accepted
10-06-2015  Land Registered (DP-1191302)
16-06-2015  PCV005 received (Electrical upgrades), Not signed
17-06-2015  Drawing minor errors amended (Dimensions of island bench)
18-06-2015  PCV006 received and accepted
23-06-2015  Land settlement completed
02-07-2015  DRP (Stockland) approval received
09-07-2015  PCV007 received and accepted
10-07-2015  DA - CDC lodgement date
15-07-2015  PCV008 received and cancelled
16-07-2015  PCV009 received and accepted
22-07-2015  CDC approval received
23-07-2015  PCV010 received, crossed out and signed (not accepted).
04-08-2015  Consolidated Documents ready
06-08-2015  Consolidated Documents received in post
07-08-2015  Consolidated Documents returned to Elderton
29-08-2015  Peg Out
04-09-2015  CONSTRUCTION START DATE
07-09-2015  Excavation completed (Cut/Fill/Level)
15-09-2015  Piering and Formwork started
16-09-2015  Internal drainage completed. Pods and reinforcements delivered.
17-09-2015  BV001 received and accepted - Garage Door Color change
18-09-2015  Slab completed
23-09-2015  Tile selection appointment
24-09-2015  External plumbing completed (Stormwater/Drainage)
14-10-2015  Frames delivered
15-10-2015  Frames up - ground floor
16-10-2015  Windows delivered
19-10-2015  Frames completed - 1st floor, windows installed
22-10-2015  Internal plumbing rough in completed
27-10-2015  Bricks delivered and ground floor started
30-10-2015  Bricks ground floor completed
05-11-2015  Scaffolding assembled
14-11-2015  Bricks first floor completed
18-11-2015  Scaffolding set-up for fascia/gutters access
23-11-2015  Fascia and gutters completed
03-12-2015  Roof sarking completed
08-12-2015  Roof tiles completed - 1st floor
20-01-2016  Eaves completed - 1st floor
22-01-2016  Facade weatherboard cladding done, bricks cleaned
05-02-2016  Downpipes and Aircon ducts partially installed
09-02-2016  Facade weatherboard cladding paint done
10-02-2016  Scaffolds down
12-02-2016  Roof tiles completed - ground floor
16-02-2016  Electrical fit-out
18-02-2016  Weatherboard cladding and garage roof completed
19-02-2016  Internal door frames installed
24-02-2016  Private pre-linings inspection by HK Ryan
26-02-2016  Inspection findings fixed
02-03-2016  Wall insulation installed
04-03-2016  Internal wall plasterboards installed
08-03-2016  Staircase installed
12-03-2016  Front and internal doors installed
13-03-2016  Cornices installed
15-03-2016  Waterproofing completed
18-03-2016  Kitchen cabinets installed
22-03-2016  Wet area tiles, bath tub, laundry tub delivered
24-03-2016  Wet area tiles started
31-03-2016  Wet area tiles completed
04-04-2016  Skirting installed
05-04-2016  Internal painting started
26-04-2016  Driveway completed
30-04-2016  Balcony handrail and privacy screen completed
03-05-2016  Carpet installed
04-05-2016  Flyscreens and strip lighting installed
09-05-2016  Paint touch-ups, staircase tread/riser stain completed
11-05-2016  House cleaning and PCI
24-05-2016  Handover