19-07-2014 Reservation of land
12-08-2014 Deposit for land
10-11-2014 Stam Duty Paid
22-11-2014 Tender requested
18-12-2014 Tender Presentation Appointment
12-01-2015 Requested for re-tender
09-02-2015 Re-tender received
11-02-2015 Tender deposit
09-03-2015 Variation 002 received and accepted
12-03-2015 Colour Selection Appointment booked for 16April
04-04-2015 DA drawings received in mail for signing
09-04-2015 Post Contract Variation (PCV) 001 received and accepted
16-04-2015 Colour Selection and Aircon Appointment DA Drawings signed
21-04-2015 Variation 003 received
22-04-2015 Electricals Appointment
05-05-2015 Amended Variation 003 received and accepted
06-05-2015 Variation 004 received and accepted
13-05-2015 Post Contract Variation (PCV) 002 received and accepted
19-05-2015 Contract signed, 5% Deposit paid
26-05-2015 Electrical quote signed and 50% deposit paid
28-05-2015 PCV 003 and 004 received and accepted
10-06-2015 Land Registered (DP-1191302)
16-06-2015 PCV005 received (Electrical upgrades), Not signed
17-06-2015 Drawing minor errors amended (Dimensions of island bench)
18-06-2015 PCV006 received and accepted
23-06-2015 Land settlement completed
02-07-2015 DRP (Stockland) approval received
09-07-2015 PCV007 received and accepted
10-07-2015 DA - CDC lodgement date
15-07-2015 PCV008 received and cancelled
16-07-2015 PCV009 received and accepted
22-07-2015 CDC approval received
23-07-2015 PCV010 received, crossed out and signed (not accepted).
04-08-2015 Consolidated Documents ready
06-08-2015 Consolidated Documents received in post
07-08-2015 Consolidated Documents returned to Elderton
29-08-2015 Peg Out
04-09-2015 CONSTRUCTION START DATE
07-09-2015 Excavation completed (Cut/Fill/Level)
15-09-2015 Piering and Formwork started
16-09-2015 Internal drainage completed. Pods and reinforcements delivered.
17-09-2015 BV001 received and accepted - Garage Door Color change
18-09-2015 Slab completed
23-09-2015 Tile selection appointment
24-09-2015 External plumbing completed (Stormwater/Drainage)
14-10-2015 Frames delivered
15-10-2015 Frames up - ground floor
16-10-2015 Windows delivered
19-10-2015 Frames completed - 1st floor, windows installed
22-10-2015 Internal plumbing rough in completed
27-10-2015 Bricks delivered and ground floor started
30-10-2015 Bricks ground floor completed
05-11-2015 Scaffolding assembled
14-11-2015 Bricks first floor completed
18-11-2015 Scaffolding set-up for fascia/gutters access
23-11-2015 Fascia and gutters completed
03-12-2015 Roof sarking completed
08-12-2015 Roof tiles completed - 1st floor
20-01-2016 Eaves completed - 1st floor
22-01-2016 Facade weatherboard cladding done, bricks cleaned
05-02-2016 Downpipes and Aircon ducts partially installed
09-02-2016 Facade weatherboard cladding paint done
10-02-2016 Scaffolds down
12-02-2016 Roof tiles completed - ground floor
16-02-2016 Electrical fit-out
18-02-2016 Weatherboard cladding and garage roof completed
19-02-2016 Internal door frames installed
24-02-2016 Private pre-linings inspection by HK Ryan
26-02-2016 Inspection findings fixed
02-03-2016 Wall insulation installed
04-03-2016 Internal wall plasterboards installed
08-03-2016 Staircase installed
12-03-2016 Front and internal doors installed
13-03-2016 Cornices installed
15-03-2016 Waterproofing completed
18-03-2016 Kitchen cabinets installed
22-03-2016 Wet area tiles, bath tub, laundry tub delivered
24-03-2016 Wet area tiles started
31-03-2016 Wet area tiles completed
04-04-2016 Skirting installed
05-04-2016 Internal painting started
26-04-2016 Driveway completed
30-04-2016 Balcony handrail and privacy screen completed
03-05-2016 Carpet installed
04-05-2016 Flyscreens and strip lighting installed
09-05-2016 Paint touch-ups, staircase tread/riser stain completed
11-05-2016 House cleaning and PCI
24-05-2016 Handover