Week 2 : Formwork done, Slab completed
Week 3 : External plumbing completed
Week 4 : --
Week 5 : --
Week 6 : Frames up - ground floor
Week 7 : Frames completed - first floor
Week 8 : Bricks - ground floor completed
Week 9 : Scaffolding assembled
Week 10 : Bricks - first floor completed
Week 11 : --
Week 12 : Fascia, Gutters completed
Week 13 : Roof sarking completed
Week 14 : Roof tiles - first floor completed
Week 15 : --
Week --- : Holiday break
Week --- : Holiday break
Week --- : Holiday break
Week 16 : --
Week 17 : Eaves - first floor, facade cladding completed
Week 18 : --
Week 19 : Downpipes and aircon ducts partially installed
Week 20 : Facade paint and roof tiles - ground floor completed
Week 21 : Cladding, door frames, garage roof, electrical rough-in completed
Week 22 : Private inspection (pre-linings/frame)
Week 23 : Wall insulation and plasterboard installed
Week 24 : Staircase and front/internal/stacker/sliding doors installed
Week 25 : Water proofing done, kitchen cabinets installed
Week 26 : Wet area tiling started (Easter weekend)
Week 27 : Wet area tiling completed. Laundry and bath tubs installed.
Week 28 : Internal painting started
Week 29 : Stonebench installed, painting completed
Week 30 : Garage door installed, nbn box installed,
Week 31 : Driveway and footpath completed, balcony handrail installed.
Week 32 : Carpet and mirror wardrobe doors installed
Week 33 : PCI
Week 34 : --
Week 35 : Handover!!!
Week 36 :
Week 37 :
Week 38 :
Week 39 :
- - - - - - - - - - - - - - - - - - - - - - - -
Week 40 :
Week 41 :
Week 18 : --
Week 19 : Downpipes and aircon ducts partially installed
Week 20 : Facade paint and roof tiles - ground floor completed
Week 21 : Cladding, door frames, garage roof, electrical rough-in completed
Week 22 : Private inspection (pre-linings/frame)
Week 23 : Wall insulation and plasterboard installed
Week 24 : Staircase and front/internal/stacker/sliding doors installed
Week 25 : Water proofing done, kitchen cabinets installed
Week 26 : Wet area tiling started (Easter weekend)
Week 27 : Wet area tiling completed. Laundry and bath tubs installed.
Week 28 : Internal painting started
Week 29 : Stonebench installed, painting completed
Week 30 : Garage door installed, nbn box installed,
Week 31 : Driveway and footpath completed, balcony handrail installed.
Week 32 : Carpet and mirror wardrobe doors installed
Week 33 : PCI
Week 34 : --
Week 35 : Handover!!!
Week 36 :
Week 37 :
Week 38 :
Week 39 :
- - - - - - - - - - - - - - - - - - - - - - - -
Week 40 :
Week 41 :