Tiles for the wet area were started before the Easter weekend. Happy with the progress, still on track.
Laundry area tiles
Common bathroom
Ensuite
First of the appliances was installed. Smeg Undermount Rangehood.
Under deck ceiling (for the porch) was completed. Stain finish to be applied after handover.
A week ago, we reported that the door that was installed was wrong (duracote door). The correct one should be a maple door with stain finish. New door was delivered and ready to replace the wrong one. **sigh***