Thursday, March 17, 2016

Doors

Architraves, door jambs and internal doors were installed. Sliding doors for the laundry and alfresco were also fitted.



We're going to look-up stage!


However, they messed up something. They installed a duracote front door (green door). Duracote doors have paint finish.  The correct door should be a maple one with a stain finish. Our supervisor will check and fix it.


Wednesday, March 9, 2016

Staircase

The staircase was installed at week 24. Slightly on track but they could do better. Neighbor building with Eden Brae, who started later than us, were at the same stage we were in.

Moving on, nice to see the staircase installed (not yet stained though). Upon entering the front door, you will not miss it. I foresaw that the staircase would be the "hero" for the forward part of the house. Upgrading it to platinum range would give the living room a little bit of a bang.

We love the appeal of an open staircase. But we opted for a closed one with an option for the under stair storage. House clutter and other knick-knacks shall definitely go in this storage.




Closed tread and risers were made of maple. Aluminium non-slip strips to be installed at the edge of the treads.


Maple post and HR45 maple handrail. Balustrade are round stainless steel.

Tuesday, March 8, 2016

Wall Plasterboards

Internal walls and ceiling linings were completed at week 23. 
 

Wall insulation and Balcony decking

Following the pre-linings inspection, installation of wall insulation was completed. Noise insulation around the house were also installed.



Timber decking for the balcony was completed but the timber ceiling (for the porch) was not yet finished. Instead of having a front door ceiling made of plasterboard only, it was decided that the timber will be extended from the porch up the front door. Sounds good. We'll see what happens.


The timber ceiling at the porch was meant to be something like this. Haven't decided yet on the stain color. The dark stain might look better though.


Independent Inspection - Pre-linings/Frame

We booked HK Ryan for the independent inspection at pre-linings stage (week 22). After the inspection, we received a detailed report right away.  There were minor issues found.  Most of the findings were in relation to frame straightening. Some walls needed additional studs, some wall braces needed to be nailed on the studs etc.  

I also ran through with our supervisor the electrical plan. Some wall plates were not installed in the proper locations. 

On that same week, the defects were fixed (as told by our supervisor). However, I have yet to receive a written confirmation from Elderton.







Saturday, February 20, 2016

Cladding, Electricals, Roof etc

Quick updates for this week;

Remaining cladding were installed at the side and back of the house.  Colorbond roofing for the garage was also completed.

Frames for the sliding doors were installed. Rangehood ducting were positioned to be vented outside.

 Kitchen bench electrical rough-ins for the outlets and strip lights.


Electrical outlets for the downlights (x15).  These were located in the family, kitchen and foyer.  All other rooms shall have battens for downlight installation after handover.


Since I'm not having NBN hub, Costa Electricals offered to provide a conduit from the garage going to the WIR. This means that the NBN box will be installed in the WIR alongside wih my router and NAS. 


WIR wirings and wall plates. Data and phone shall be running out from the WIR to other data points in the house. 

 TV antenna splitter


Data point and TV Antenna point


Meter Box 





Saturday, February 13, 2016

Roof Tiles - Ground Floor

Before the week ended, ground floor roof tiles were completed at the back part of the house (alfresco and media room).


Alfresco roof sarking


Aircon ducting


Colorbond roofing (at the garage) was left to be done. This was scheduled for the following week, alongside with the electrical fit-out.