Saturday, April 2, 2016

Tiles - Wet Area Completed

As we head down the home stretch, we were assigned with a new supervisor. The previous site supervisor (who was the Area Manager) had to take on upcoming projects. It is not the best news as our previous supervisor was very good. Last thing we wanted for the final stages of our build is to become pear-shaped. 

To begin with, not much work done this week aside from the completion of the tiling on the wet areas. Bath tub and laundry tub were installed.


Skirting were ready to be installed.



Now, to be on track, we have another 4 weeks left before Practical Completion Inspection. What is expected for next week should be the completion of the painting, electrical/plumbing and fix out carpenter to finish off.  

To cap off, here's a photo of the house after week 27. Nothing has changed in the exterior though.

Friday, March 25, 2016

Tiles - Wet area

Tiles for the wet area were started before the Easter weekend. Happy with the progress, still on track.

Laundry area tiles


Common bathroom


Ensuite


First of the appliances was installed. Smeg Undermount Rangehood.


Under deck ceiling (for the porch) was completed. Stain finish to be applied after handover.


A week ago, we reported that the door that was installed was wrong (duracote door).  The correct one should be a maple door with stain finish. New door was delivered and ready to replace the wrong one. **sigh***


Tuesday, March 22, 2016

Kitchen Cabinets et al.

Kitchen cabinets were installed before the Easter weekend. The overhead cabinets looks sweet!! 


 Bathtub and laundry tub delivered

Timber skirting for ground floor ready to be installed.


 Bathroom/Laundry tiles delivered.

Cutouts were done for the electrical outlets and powerpoints. Mounting clips were also installed.



Thursday, March 17, 2016

Waterproofing

Waterproofing completed.  


Skirting installation was also completed on the first floor.


Cornices installed.


Next up, kitchen cabinet installation.



Doors

Architraves, door jambs and internal doors were installed. Sliding doors for the laundry and alfresco were also fitted.



We're going to look-up stage!


However, they messed up something. They installed a duracote front door (green door). Duracote doors have paint finish.  The correct door should be a maple one with a stain finish. Our supervisor will check and fix it.


Wednesday, March 9, 2016

Staircase

The staircase was installed at week 24. Slightly on track but they could do better. Neighbor building with Eden Brae, who started later than us, were at the same stage we were in.

Moving on, nice to see the staircase installed (not yet stained though). Upon entering the front door, you will not miss it. I foresaw that the staircase would be the "hero" for the forward part of the house. Upgrading it to platinum range would give the living room a little bit of a bang.

We love the appeal of an open staircase. But we opted for a closed one with an option for the under stair storage. House clutter and other knick-knacks shall definitely go in this storage.




Closed tread and risers were made of maple. Aluminium non-slip strips to be installed at the edge of the treads.


Maple post and HR45 maple handrail. Balustrade are round stainless steel.

Tuesday, March 8, 2016

Wall Plasterboards

Internal walls and ceiling linings were completed at week 23.